Jackson Avenue Improvement Project — Week 26

The renovation work for Jackson Avenue has come to a halt. When will this project be completed?

There was hardly any activity by the construction crews on the Jackson Avenue Improvement Project this week.

Cement for the sidewalk and the new curb in front of on the corner of Ira Road was poured on Monday.

On Thursday morning, a utility crew was working on the electricity for the new decorative street lighting in front of the businesses named above.

Find out what's happening in Syossetwith free, real-time updates from Patch.

What the coming week will bring is anyone's guess. Let's hope that they begin laying the final layer of asphalt from Pine Road to the LIRR, followed by the completion of the striping for the traffic lanes for the same stretch of avenue.

We will just have to wait and see.

Find out what's happening in Syossetwith free, real-time updates from Patch.

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?