This post was contributed by a community member. The views expressed here are the author's own.

Health & Fitness

Jackson Avenue Improvement Project — Week 27

This week, community residents saw the completion of the major Jackson Avenue Improvement Project construction with the laying of the final coat of asphalt from Pine Road to the LIRR crossing.

This was the week that we have all been waiting for... the conclusion of the major work of the Jackson Avenue Improvement Project.

On Wednesday, the construction crews prepped the avenue for the final layer of asphalt from Pine Road to the LIRR crossing. 

Early Thursday morning, the heavy construction equipment arrived, followed by the arrival of the trucks containing the asphalt. The crews worked the entire day, and the rain did not deter them from completing their task. They started at the LIRR crossing and worked their way south to Pine Road. 

Find out what's happening in Syossetwith free, real-time updates from Patch.

On Friday, the workers from Safety Marking, Inc. began to stripe the lanes and put down the directional arrows in the center turn lane. The striping for the lanes and crosswalks was completed by Saturday morning.

A "punch list" has been compiled of some small items that need to be completed along the avenue, such as the laying of decorative brick to complete the sidewalks by and the Councilman's office. 

Find out what's happening in Syossetwith free, real-time updates from Patch.

The reconstruction of Jackson Avenue, discussed and planned over the past ten years, is now a reality and it took only 27 weeks. 

Enjoy your drive along the avenue as you travel it during this holiday week. Happy Thanksgiving!

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?